Watch·Them·Work
Government Procurement Authority Index Volume II
saved
12 MAY 2026
Subject of file

Gaelscoil Dara (Gaillimh)

file no.2243 active2017-05-31 – 2022-06-16 suppliers1 spend areas2
Contracts
4
Total committed
€0
Solo / framework
1 / 0
Period
2017-05-31 – 2022-06-16
year
procedure

Top suppliers

click to filter
  1. 01 ProAir Heat Recovery Ventilation Systems 1

Spend areas

click to filter
  1. 01 Construction work. 1
  2. 02 Advisory architectural services. 1

Contract listing

4 records
Date Contract Suppliers Procedure Awarded
2022-06-16 Ventilation Services to Classrooms ProAir Heat Recovery Ventilation Systems Open Procedure
2021-04-09 New Handball Court Building Open Procedure
2019-06-06 Gaelscoil Dara Galway Open Procedure
2017-05-31 430m² two-storey extension to existing 16 classroom school Open Procedure