Lough Ree Lanesborough Angling Hub

file no.3171 active2019-03-28 – 2021-10-23 suppliers2 spend areas1
Contracts
3
Total committed
€0
Solo / framework
2 / 0
Period
2019-03-28 – 2021-10-23
year
procedure

Top suppliers

click to filter
  1. 01 James Irwin Construction 1
  2. 02 Alunaut 1

Spend areas

click to filter
  1. 01 Construction work. 1

Contract listing

3 records
Date Contract Suppliers Procedure Awarded
2021-10-23 Fit out of existing toilet and chaning rooms at Lough Ree Angling Hub James Irwin Construction Open Procedure
2019-07-09 Construction of Lough Ree ‘Access For All’ Outdoor Recreational Centre, Lough Ree Angling Hub, Ballyleague, Co. Roscommon, N39 E297, Open Procedure
2019-03-28 Wheelchair Accessible Passenger Boat & Boat Trailer Alunaut Open Procedure