Watch·Them·Work
Government Procurement Authority Index Volume II
saved
12 MAY 2026
Subject of file

Na Píobairí Uilleann (NPU)

file no.2498 active2024-04-03 – 2025-05-27 suppliers1 spend areas2
Contracts
2
Total committed
€1.60M
Solo / framework
1 / 0
Period
2024-04-03 – 2025-05-27
year
procedure
clear all

Top suppliers

click to filter
  1. 01 Mullarkey Pedersen Architects 1

Spend areas

click to filter
  1. 01 Construction work. 1
  2. 02 Architectural, construction, engineering and inspection services. 1

Contract listing

1 of 2 · €0
Date Contract Suppliers Procedure Awarded
2025-05-27 Works Contractor for Construction of New Extension and Refurbishment Works for Sound of Ireland Centre Project at 16 Henrietta Street, Dublin 1, D01 N504 For Na Píobairí Uilleann TED Restricted Procedure