| Date | Contract | Suppliers | Procedure | Awarded |
|---|---|---|---|---|
| 2024-07-30 | RFT for the Expansion of Gates 1 – 5 at Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | €2.39M |
| 2024-07-12 | RFT - Refurbishment and Alteration of the Main Toilet and Welfare Facilities at Shannon Airport Arrivals Hall, Shannon Co. Clare CAN | M Fitzgibbon Contractors Ltd | Open Procedure | €469k |
| 2024-04-10 | Request for Tender for Hangars 3 and 4 Door Replacement (Design and Build) at Shannon Airport CAN | M Fitzgibbon Contractors Ltd | Open Procedure | €330k |
| 2024-03-15 | Supply and Installation of two new lifts along with associated works at the Shannon Airport CAN | M Fitzgibbon Contractors Ltd | Open Procedure | €524k |
| 2022-10-04 | Proposed Foul Pumping Station Supply & Installation and Hydrocarbon Remediation Works at Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2022-08-04 | Shannon Airport Authority DAC is seeking competitive quotes for the electric vehicle charging infra-structure works at Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2022-07-27 | Construction works relating to Phase 2 Extension to Shannon Airport Fire Station & Kitchen Refurbishment | M Fitzgibbon Contractors Ltd | Competitive Procedure With Negotiation | — |
| 2021-03-18 | The Provision of a 36-Month Plant and Equipment Hire Framework for Shannon Airport Authority DAC | framework · 5 Kiltane Service Station Ltd, M Fitzgibbon Contractors Ltd, Mike Meade Services +2 |
Open Procedure | — |
| 2020-10-15 | Shannon Airport Fire Station Wet Areas Upgrade Works | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2019-04-17 | RFT for Floor Replacement Works at Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2018-04-10 | Fire Training Ground Phase 2 - Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2017-11-01 | RFT for Fire Station Extension Works - Revised Scope of Works | M Fitzgibbon Contractors Ltd | Open Procedure | — |
| 2017-01-30 | RFT for the Refurbishment of Swissport OTB Offices, Shannon Airport | M Fitzgibbon Contractors Ltd | Open Procedure | — |