| Date | Contract | Suppliers | Procedure | Awarded |
|---|---|---|---|---|
| 2024-07-17 | N72 Fossa Traffic Calming and Enhanced Cyclist and Pedestrian Improvement Scheme | Sorensen Civil Engineering Ltd | Open Procedure | €3.98M |
| 2023-03-30 | N70 Creamery Cross to Kenneigh Phase 1 and TII HD28 2023 | Roadstone ltd. | Open Procedure | — |
| 2022-10-14 | N70 Gleensk Pavement Improvement Scheme | Roadstone ltd. | Open Procedure | — |
| 2021-11-26 | N69 Upper Church Street, Listowel Pavement & Safety Improvement Scheme | Glas Civil Engineering Ltd | Open Procedure | — |
| 2019-01-09 | MINOR PAVEMENT MAINTENANCE WORKS FOR NATIONAL ROAD SCHEMES | — | Open Procedure | — |
| 2018-07-10 | HD 28 Retextruing 2018 | — | Open Procedure | — |